| From
Tehelka Magazine, Vol 5, Issue 48, Dated Dec 06, 2008 |
|
|
Power Play
While UP reels under a huge shortfall of power,
the Mayawati Government is more interested in
the politics of power, says SRAWAN SHUKLA
|
| Illustration: NAOREM ASHISH |
IF THEWorld Bank can use its international
clout and propose reform,
only the hurly-burly of Indian politics
can dispose of such reform. The
global financial institution has pumped
in as much as $4 billion and forced a
modicum of reform in the power sector
across India. But in Uttar Pradesh, the
state continues to lag behind others.
Worse, the government is not ensuring
that the commissioning of eight new
plants in the public and private sector
occurs within the Eleventh Five-Year-
Plan period. The result: the power situation
is so grim that except for Lucknow,
the other 70 districts do not get 12 to 16
hours of supply.
There are eight new thermal power
plants envisaged: Paricha (500 MW),
Harduaganj (500 MW), Anpara D (500
MW) and Obra (1,000 MW) in the public
sector; Anpara C (1,200 MW), Roja (1,200
MW), Bara (1,980 MW) and Karchana
(1,320 MW) in the private sector. Together
they should add installed capacity
of 7,200 MW by 2011. But except for Roja,
being set up by Anil Ambani’s Reliance
Power, none of the others seem to be in
any state to come up. The causes: increasing
political interference, rampant
corruption and the slow pace of work.
If that isn’t enough, another power
plant at Dadri in the private sector is
caught in a row between the Ambani
brothers on supply of gas. The Mulayam
Singh government had made available
2,500 acres of land at subsidised rates
in 2003 for the Rs 10,000-crore gasbased
3,740 MW plant to Reliance Power
despite farmers’ protests. According to
the original agreement, it was to begin
from 2008. But there is no sign of the
project starting.
The state has a capacity for generating
4,700 MW thermal and hydro power,
leaving a huge gap of 3,500 MW to 4,000
MW. But while the work is slow at least in
the four projects in the public sector, the
fate of the new projects in the private
sector looks far less certain.
Even after three biddings, the
Mayawati Government has failed to
take any decision on the Bara and
Karchana power projects in Allahabad
district. Over 1,000 acres of land for
both projects has already been acquired
in Shankergarh Tehsil by the UP Power
Corporation Limited (UPPCL), but there
seems to be no decision taking place to
award the contract to the lowest bidders.
Earlier this year, UPPCL invited global
biddings for two mega projects. While
NTPC, Indiabulls, Lanco Kondapalli
Power Limited, GVK, L&T, Adani, Reliance
Power and Isolux Corsan had
shown interests in Bara; Lanco Kondapalli
Power Ltd, Reliance Power, CESE,
KSK Energy, Indiabulls, HDIL Energy,
Bhushan Steels, GVK, Adani, JSW and L&T
had submitted a Request for Qualifications
(RFQ) for Karchana.
Bids were invited on ‘levelised tariff’
for 25 years in June 2008. On opening
of bids, Rs 2.84 per unit, quoted by Lanco
Kondapalli Power Limited, was declared
as the lowest bidder (L1). But the Uttar
Pradesh Government cancelled the bidding
on the pretext that the rate quoted was on the higher side. Soon after the
first bid, the state government revised the
RFQ. It increased the plant capacity to
2X660 MW in the case of Karchana and
3X660 MW for Bara, and allowed the
bidders to sell 80 percent of the power
generated from the extra capacity in the
open market. “It was done to meet the Central Vigilance Commission guidelines
of explaining reasons for inviting
second biddings, but at the cost of the
state’s interests,” charges Shailendra
Dubey, Secretary-General, All-India
Power Engineers’ Federation.
IN THE second bidding, Reliance
Power emerged as the lowest bidder
(L1) with a price of Rs 2.60 per unit.
But the state government scrapped this
bid also, charging Reliance Power with
manipulating the L1 by quoting ‘practically
and theoretically’ impossible variable
charges. Though Reliance Power
officials deny the charge, a senior UPPCL officer told TEHELKA that Reliance
Power calculated the
charges by claiming a heat
rate as low as five kilo calories
for generating one unit of
power, while the same was a
minimum 2,150 kilo calories
per unit for Indian thermal
power plants. “It was impossible.
Accepting that price
would have resulted in great
loss to the state as the project
would have become unviable
after a few years due to the
increasing price of coal,” says
the official.
The third round of bidding
for Karchana was submitted
in October 2008. When bids
were opened, Jaypee Associates,
a group closer to the present political
dispensation, was found to be a
surprise bidder. The company, which
had so far evinced no interest, emerged
as the lowest bidder with a price of Rs
2.97 per unit, followed by Adani’s Rs 2.98
per unit, and Lanco’s Rs 3.18 per unit.
Reliance Power, which had offered the
lowest in the second bid, quoted a tariff
of Rs 3.98 per unit. The rate quoted by
Jaypee was 0.37 paise and 0.13 paise
higher than those quoted by Reliance
and Lanco respectively. Going by the
1,320 MW capacity of the proposed
Karchana project, it will generate about
925 crore units of power every year. Provided
that the heat rate calculations were
correct, this could mean a loss to the
state of Rs 320 crore a year if the contract
was awarded to Jaypee Associates.
The bidding process has raised hackles,
with officials finding it difficult to
justify the cancellation of the earlier
biddings and a possible award of the
contract to Jaypee Associates at a higher
tariff. Both Lanco and Reliance officials
say awarding Jaypee the contract
will be a grave injustice
to them. “My company had
offered the most competitive
and lowest price but it was
rejected to accommodate
the government’s favourite,”
charges a vice-president of
Reliance Power, on condition
of anonymity.
The state government is
now trying to persuade
Japyee to reduce the quoted
tariff by 0.10 paise to avoid
controversy. A high-level
meeting, under the chairmanship
of Uttar Pradesh
Chief Secretary Atul Kumar
Gupta, was held in Lucknow
on 21 November with a sixmember
delegation from Japyee, where
the company was pressed to reduce the
tariff. But Jaypee, which was earlier
awarded the Rs 40,000-crore Ganga
Expressway project by the present
regime, has refused. “The meltdown and
substantial hike in the construction cost
does not allow us to reduce tariffs. The
company has already quoted a competitive
price and the government should
award the contract at the earliest to
avoid further delay and increase in cost,”
Jaypee officials told the government.
Now the state government is in a fix.
If it awards the contract to Japyee Associates,
the issue might land into a legal
tangle or kick up a row and give a tool to
the opposition before the Lok Sabha
polls. “The entire exercise is a farce. The
government should scrap the bidding
and give both the projects to BHEL or
NTPC to avoid delay and controversy,”
suggests Dubey.
When contacted, Avinish Awasthi,
MD of UPPCL, said that “the government
has not taken any decision yet on bids
for Karchana”, adding, “We are in the
process of evaluating bids and take a decision
once the processends,” refusing to
make any comment on the two projects.
Clearly, while the politics takes centre-
stage, business sense and public need
seem to have taken a backseat.
WRITER’S EMAIL:
srawan@tehelka.com |